Swires Cold Storage

Asbestos Re-Roof Lurnea

  • Roofing Replaced

    5,500 ㎡

  • Completion Time

    6 days

One of Lidoran's many asbestos re-roofing projects.

With two asbestos roofs of 5,500 square metres to be removed & replaced the Lidoran crew completed the works in 3 shutdown windows over 3 weekends.

A full internal vacuum clean was also done on completion.