St Peter’s Presbyterian Church Hall

  • Roofing Replaced

    300 ㎡

  • Completion Time

    24 hours

Lidoran Group stripped & replaced 300 square metres of asbestos off the church hall.

Although this project was on a smaller scale; the works still had their own share of difficulties; in a very built up residential area & lots of weekend activity.

Lidoran overcame these difficulties completing the roof on the same day with a crew of 8 tradesmen.